14
INSTALLATION AND OPERATION MANUAL 25-16732-A November 2019 www.eaton.com
•
Once the cable entry holes have been cut then fit the cable
glands to the back box.
•
If the panel is being flush mounted, then insert the panel
into the recess feeding the cables through the rear cable
entry points.
•
If the panel is being wall mounted then cut out the required
number of cable entry holes in the back using a 20mm hole
saw with pilot drill bit as shown in Figure 19. Fit the glands
to the back box and pull through the required cables.
•
Using the mounting holes in the back box, drill holes into
the wall and insert wall plugs and secure the panel to the
wall as shown in Figure 20. Ensure any dust is cleaned from
the back box.
•
Secure the PSE PCB back into the back box by following the
reverse instructions in Figure 18.
•
Fit the PCB shelf and cables by following the reverse
instructions in Figure 16 and Figure 17 on page 13.
•
If the panel is wall mounted, pull the cabling through the
glands ready for wiring.
•
Fit the door back onto the back box by following the reverse
instructions in Figure 15.
Figure 19. Cut cable entry holes
Figure 20. Secure the panel to the wall