Fire Outputs & Battery Check
WARNING
THIS TEST WILL ACTIVATE ANY EXTERNAL EQUIPMENT
CONNECTED TO THE FRE, FPE OR FIRE RELAYS. IF THE
ACTIVATION OF THE EQUIPMENT IS NOT DESIRED THEN
THE EQUIPMENT MUST BE DISABLED, DISCONNECTED
OR POWERED OFF DURING THIS TEST AND RESTORED
ONCE THE TEST IS COMPLETE.
Measure the battery charger voltage, this should be
around 27.6V.
Disconnect the mains supply and check the following:
•
Power On (green) indicator is still on.
•
General fault (amber) indication is on.
•
Battery/Mains fault indication is on for mains fault.
The panel should not lose power during the following test.
Activate a call point in any zone.
Check the following on the panel:
•
General fire indicator (red) is on.
•
Correct zone fire indicator (red) is on.
•
FRE On indicator (red) is on.
•
FRE output has switched to 24V (if fitted).
•
FPE output has switched to 24V (if fitted).
•
Fire relay has switched over to C/NO.
•
All fire alarm devices are sounding.
Check the following on the interlinked panel (if installed):
•
General fire indicator (red) is on.
•
FRE On indicator (red) is on.
•
FRE output has switched to 24V (if fitted).
•
FPE output has switched to 24V (if fitted).
•
Fire relay has switched over to C/NO.
•
All fire alarm devices are sounding.
Perform a soft reset and then check that the panel and
interlinked panel have returned to the normal condition with
mains fault.
4. Commissioning & System Handover
4.1 Commissioning
The walk test feature (see “Walk Test Mode” on page
26 for more details) has been provided to facilitate the
commissioning of the BiWire Flexi.
system. The commissioning of the system should be
conducted in accordance to BS5839 part 1 Annex H.
The commissioning certificate must be completed and any
variances noted.
The system configuration and variances should be recorded on
the log book.
4.2 System Handover
The following documents must be handed over to the
Premises Management of the installation:
•
Zone map
•
Commissioning certificate
•
Log book
•
User Manual
The Premises Management will be demonstrated the
operation of the system and given basic training on the
operation of the system and filling in the log book.