Eaton BladeUPS DoS Installation Instructions P-164000613—Rev 3 7
Figure 4. Dial Set to UPS Position
4. Verify utility power is switched off to the distribution point where the UPS system will be connected.
CAUTION
Be absolutely sure there is no power.
5. In the floor of the front of the cabinet, unbolt the two bolts that secure the cabinet to the pallet with a 9/
16” socket. Remove the bolts along with the associated lock washers and flat washers (see Figure 5).
Figure 5. Remove Two Bolts in Front Cabinet Floor
6. Use a 7 mm socket to remove the back cabinet top and back covers (see Figure 6). Retain the covers and
the hardware you removed to replace them after the wiring is completed.
Figure 6. Remove Back Covers
7. After the back covers are removed, locate the back bolts that secure the cabinet to the pallet. Use a 9/16”
socket to remove the bolts and retain the hardware you removed.
Note: If you are using a transformer in your BladeUPS system configuration, make sure the transformer is at
the final installation location.