8 Eaton BladeUPS DoS Installation Instructions P-164000613—Rev 3
8. Move and secure the BladeUPS cabinet:
a. If you are using a NEW or an EXISTING transformer: Lift the BladeUPS cabinet on top of the
transformer and align it without overhang (see Figure 7). With a 9/16” socket, secure the cabinet to
the transformer with the same bolts, locking washers, and flat washers that previously secured the
cabinet to the pallet.
b. If you are NOT using a transformer: Bolt the cabinet to the floor.
Figure 7. Lift BladeUPS Cabinet on Top of the Transformer