14 Eaton BladeUPS DoS Installation Instructions P-164000613—Rev 3
Figure 16. BladeUPS Cabinet Back Panel View
Input-Output Wire
For each UPS, connect the Input-Output Wire (see Figure 16).
Hot Sync CAN Bridge Cards
a. Unpack the Hot Sync CAN Bridge Cards and verify that the cards were not damaged during shipment.
b. Install the first Hot Sync CAN Bridge Card into the open X-Slot communication bay on the top UPS
(see Figure 17).
c. Install the second Hot Sync CAN Bridge Card into the open X-Slot communication bay on the bottom
UPS (see Figure 17).
Blue Terminating Plugs
a. Install a blue terminating plug in the CAN IN port on the top UPS (see Figure 17).
b. Install a blue terminating plug in the CAN OUT port on the bottom UPS (see Figure 17).
Input-Output
Hot Sync CAN Bridge Card Bay
Blue Terminating
CAN Bridge Card
Redundant
Load Connector
CB1 Input
CB2 Input
Cable Connection
Plug Connection