16 Eaton BladeUPS DoS Installation Instructions P-164000613—Rev 3
Note: When you connect the cables between the UPS units make sure that you route them through the
grommets in the UPS lower brackets (see Figure 18).
Figure 18. Cable Grommets
Redundant Signal Cable
a. Install a redundant signal cable between the Standalone/Parallel terminal on the top UPS and the
COM For Parallel Use Only terminal on the bottom UPS (Figure 19).
b. Be sure to check correct polarity when installing the cable.
CAUTION
If polarity or wiring is not correct, the parallel system does not operate normally. For example, when
shutting down one UPS, the remaining UPS transfers the load to bypass instead of supporting the load.
Verify that all wiring is correct for proper operation.
HARNESS
P-1520012376
Grommets
Grommets
Zip Tie
Zip Tie
11/12 TERMINATION
"ON BYPASS SIGNAL"
Zip Tie