INSTALLATION
Eaton BladeUPS Bar Installation Guide S 164201723 Rev 2 www.eaton.com/powerquality
10
12. Secure the bar to the wireway with three M6 12 hex bolts. Install
the bolts from the front of the rack. See Figure 5. Torque the bolts
to 5.1 ± 0.8 Nm (45 ± 7 lb in).
13. Reinstall the terminal block assembly bracket removed in Step 10.
Install the bolts from the front of the rack. See Figure 5. Torque the
bolts to 5.1 ± 0.8 Nm (45 ± 7 lb in).
NOTE Do not change the original orientation of the terminal block assembly bracket. Verify
that the threaded holes mount to the rack, not to the bar.
Rear of Rack
Front of Rack
Terminal Block
Assembly Bracket
M6 12 Hex Bolts
(3 places)