P-164000476 9395P 500kVA / 600 kVA 11
Revision 002 Userās and Installation Guide
3 UPS installation plan and unpacking
Use the following basic sequence of steps to install the UPS:
1. Create an installation plan for the UPS system (Chapter 3).
2. Prepare your site for the UPS system (Chapter 3).
3. Inspect and unpack the UPS cabinet (Chapter 3).
4. Unload and install the UPS cabinet, and wire the system (Chapter 4: āUPS system installationā).
5. Complete the installation checklist at the end of this manual.
6. Have authorized service personnel perform preliminary operational checks and startup.
Startup and operational checks must be performed by an authorized Eaton Customer Service
Engineer, or the warranty terms specified on page 123 become void. This service is offered as
part of the sales contract for the UPS. Contact service in advance (usually a two-week notice is
required) to reserve a preferred startup date.
3.1 Creating an installation plan
Before installing the UPS system, read and understand how this manual applies to the system being
installed. Use the procedures and illustrations in Section 3.2 and Chapter 4: āUPS system installationā
to create a logical plan for installing the system.
3.2 Preparing the site
For the UPS system to operate at peak efficiency, the installation site should meet the environmental
parameters outlined in this manual. If the UPS is to be operated at an altitude higher than 1000 m,
contact your service representative for important information about high altitude operation. The
operating environment must meet the weight, clearance, and environmental requirements specified.