Eaton Power Xpert 9395 UPS Installation and Operation Manual 164201764—Rev 14 67
neutral terminals in the ISBM section. See paragraph 3.2.4 UPS System Power Wiring Preparation for
wiring and termination requirements.
8. If wiring a distributed bypass system, proceed to Step 9; otherwise, proceed to Step 11.
9. Using hardware from the external wiring terminal hardware kit (see Table 14), connect phase A, B, and C,
and Neutral power wiring from the output and neutral terminals of each UPS unit to the customer-supplied
tie cabinet or load distribution panel. See paragraph 3.2.4 UPS System Power Wiring Preparation for wiring
and termination requirements.
10. Proceed to paragraph 4.8.2 Battery Power Wiring.
11. Using hardware from the external wiring terminal hardware kit (see Table 14),connect phase A, B, and C,
and Neutral (if required) power wiring from output terminals and neutral terminals to the critical load. See
paragraph 3.2.4 UPS System Power Wiring Preparationfor wiring and termination requirements.
12. Proceed to paragraph 4.8.2 Battery Power Wiring.