Commissioning Deltabar S FOUNDATION Fieldbus
44 Endress+Hauser
Closed container
• All Deltabar S versions are suitable for level measurement in closed containers.
• FMD77: the device is ready for calibration immediately after opening the shutoff valves (may
or may not be present).
• FMD78: the device is ready for calibration immediately.
• PMD75: before calibrating the device, the pressure piping must be cleaned and filled with
fluid. See the following table.
Valves Meaning Installation
1 Fill container to a level above the lower tap.
P01-xMD7xxxx-11-xx-xx-xx-004
Fig. 13: Closed container
I Deltabar S PMD75
II Three-way valve manifold
III Separator
1, 2 Drain valves
2, 4 Inlet valves
3 Equalizing valve
6, 7 Vent valve on Deltabar S
A, B Shutoff valve
2 Fill measuring system with fluid.
Close 3. Shut off positive side from
negative side.
Open A and B. Open shutoff valves.
3 Vent positive side (empty negative side if necessary).
Open 2 and 4. Introduce fluid on positive
side.
Open 6 and 7 briefly, then
close them again.
Fill positive side
completely with fluid and
remove air.
4 Set measuring point to operation.
Now
– 3, 6 and 7 are closed.
–2, 4, A and B are open.
5 Carry out calibration.
ä 46, Section 7.7.2.