PROline Promag 53 3 Installation
Endress+Hauser 45
3.4 Instal lati on check
Perform the following checks after installing the measuring device in the pipe:
Device condition and specifications Notes
Is the device damaged (visual inspection)?
−
Does the device correspond to specifications at the measuring point,
including process temperature and pressure, ambient temperature,
minimum fluid conductivity, measuring range, etc.?
seePage121
Installation Notes
Does the arrow on the sensor nameplate match the direction of flow
through the pipe?
−
Is the plane of the measuring-electrode axis correct? Horizontal
Is the position of the Empty Pipe Detection (EPD) electrode correct? see Page 17
Were all threaded fasteners tightened to the specified torques when
the sensor was installed?
see Section 3.3
Hard rubber lining and ground disks:
Were the correct seals installed (type, material, installation)?
Promag W
→ Page 26
Promag P
→ Page 32
Promag H
→ Page 38
Are the measuring-point number and labeling correct (visual inspec-
tion)?
−
Process environment / process conditions Notes
Are there enough inlet and outlet runs available? Inlet run
≥ 5 x D
Outlet run
≥ 2 x D
Is the measuring device protected against moisture and direct
sunlight?
−
Is the sensor adequately protected against vibration (attachment,
support)?
Acceleration up to 2 g by
analogy with IEC 68-2-6