PROline Promag 53 6 Commissioning
Endress+Hauser 83
6 Commissioning
6.1 Function check
Make sure that all final checks have been completed before you start up your measuring
point:
• Checklist for “Installation check” → Page 45
• Checklist for “Electrical connection check” → Page 60
6.2 Commissioning
6.2.1 Switching on t he measuring device
Once the connection checks (see Page 60) have been successfully completed, it is
time to switch on the power supply. The device is now operational.
The measuring device performs a number of post switch-on self-tests. As this proce-
dure progresses the following sequence of messages appears on the local display:
Normal measuring mode commences as soon as start-up completes. Various
measured-value and/or status variables (HOME position) appear on the display.
!
Note:
If start-up fails, an error message indicating the cause is displayed.
PROMAG 53
START-UP
RUNNING
Start-up message
▼
PROMAG 53
SW AMPLIFIER
V XX.XX.XX
Current software version (example)
▼
CURRENT OUTPUT
FREQUENCY OUTPUT
RELAY
STATUS INPUT
List of installed input/output modules
▼
SYSTEM OK
→ OPERATION
Beginning of normal measuring mode
▼