Installation Proline Prowirl R 200 HART
28 Endress+Hauser
A0019209
9 Layout for delta heat measurement of saturated steam and water
1 Measuring device
2 Temperature sensor
3 Heat exchanger
Q Heat flow
Protective cover
Observe the following minimum head clearance: 222 mm (8.74 in)
For information on the weather protection cover, see → 169
6.2 Mounting the measuring device
6.2.1 Required tools
For transmitter
• For turning the transmitter housing: Open-ended wrench8 mm
• For opening the securing clamps: Allen key3 mm
• For turning the transmitter housing: Open-ended wrench8 mm
• For opening the securing clamps: Allen key3 mm
For sensor
For flanges and other process connections: Corresponding mounting tools
6.2.2 Preparing the measuring device
1. Remove all remaining transport packaging.
2. Remove any protective covers or protective caps present from the sensor.
3. Remove stick-on label on the electronics compartment cover.
6.2.3 Mounting the sensor
L
WARNING
Danger due to improper process sealing!
‣
Ensure that the inside diameters of the gaskets are greater than or equal to that of the
process connections and piping.
‣
Ensure that the gaskets are clean and undamaged.
‣
Install the gaskets correctly.