5.4 Commissioning
Before switching the measuring equipment on for the first time repeat the following
checks:
• Check the electrical connections and the allocation of the terminals.
• Compare the data on the nameplate with the local mains voltage and frequency.
• Does the direction of the arrow on the nameplate (sensor) agree with the actual
direction of flow in the piping?
If the results of these checks are satisfactory, switch on the supply voltage.
The unit is ready for operation.
5. Operation and Commissioning Promag 30
44 Endress+Hauser