3.3.2 Wiring Procedure
Prepare the following items before preparing the wiring for the Main Circuit Terminals and Control
Circuit Terminals.
Commercially available screwdriver with tip width of 3.0 mm to 3.5 mm
Sleeve type ferrule with cross-section from 1.5 mm
2
to 2.5 mm
2
Commercially available plier with crimping and stripping functions
Follow the procedure below to wire the Main Circuit Terminals and Control Circuit Terminals.
Step 1 Remove the Main Circuit Terminals and Control Circuit Terminals from the Drive.
Figure 3-2 Remove the terminals
Step 2 Peel off the sheath so that the conductor portion of the cable will protrude from the tip of the ferrule.
Figure 3-3 Remove the sheath
Step 3 Insert the cable into the ferrule (It should protrude 1 mm or more from the ferrule).
Figure 3-4 Insert the cable into the ferrule