EVCO S.p.A. EVJ800 | Installer manual ver. 1.0 | Code 144J800E104
page 30 of 48
freezing;
see also parameter r5
r4 -18 -50 99 °C
Product temperature to end temperature controlled blast
freezing;
see also parameter r6
r5 90 1 500 min
Maximum permitted duration for temperature controlled blast
chilling;
see also parameter r3
r6 240 1 500 min
Maximum permitted duration for temperature controlled blast
freezing;
see also parameter r4
r7 0 -50 99 °C
Cabinet temperature setpoint during blast chilling and the soft
phase of soft blast freezing;
see also parameter r0
r8 -40 -50 99 °C
Cabinet temperature setpoint during blast freezing and ice
cream hardening;
see also parameter r0
r9 -20 -50 99 °C
Cabinet temperature setpoint during the hard phase of hard
blast chilling;
see also parameter r0
r10 2 -50 99 °C
Cabinet temperature setpoint during conservation after blast
chilling and hard blast chilling;
see also parameter r0
r11 -20 -50 99 °C
Cabinet temperature setpoint during conservation after blast
freezing and soft blast freezing;
see also parameter r0
r12 5 -50 99 °C
Cabinet temperature setpoint during pre-cooling;
see also parameter r0
r13 15 -50 99 °C
Product temperature to end the hard phase of hard temperature
controlled blast chilling
r14 60 10 100 %
Duration of the hard phase of hard time controlled blast chilling
(i.e. the percentage of the value set by parameter r1). Duration
of the soft phase of time controlled soft blast freezing (i.e. the
percentage of the value set by parameter r2)
r15 65 -50 199 °C
Product temperature below which the count for maximum
duration begins for temperature controlled blast chilling or blast
freezing
r17 5 0 99 °C
Minimum gap between the product and cabinet temperatures,
according to which the first phase of the test for correct
insertion of the needle probe is considered successfully
completed
0 = the test is disabled and the needle probe is considered
always inserted
r18 80 10 999 s
Duration of the second phase of the test for correct insertion of
the needle probe
r19 -40 -50 +99 °C Cabinet temperature setpoint for the first phase of sanitation