A
A
A
A
D
B
x18
Note: The number of screws can be
reduced according to the size of the
workbench.
Place lumber (d) on the triangle fixed plates ③, and place board (a) on the top of table
to complete the installation of workbench.
Then, fix the top, middle and lower layers of boards and lumbers with screw (b) (the
position of the screws should be at the equal-division points).
Insert shelf holder ④ to lumber (g) as direction shown below.
Use cordless power drill to fix them with screw (a) x 12.
4 sets in total.
Place board (e) and board (f) on the shelf holder set as shown below.
Use cordless power drill to fix them with screw (a) x 8.
Place shelf on workbench as shown below.
Use cordless power drill to fix them with screw (a) x 8.
Note: The position of middle shelf
holder can be adjusted according to
demand, but the two sets must be
horizontal.