Frontgate 49226 - Option Two: Post Installation with 2 x4 Support

Default Icon
3 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Step 2 Step 3
Step 4
Option Two:
1. Follow same steps as above.
2. After you have poured the concrete, place a pressure treated 2X4 in the concrete so that it
goes down at least two feet or more into the ground and sticks up no more than two feet
above ground.
3. Slide the post over the 2X4 and into the concrete up to the lip on the post. Ensure the post
and 2X4 are vertical.
4. Put the Part A cover on the top of Part B body of post.
5. Wait until the concrete sets up before mounting the hose reel to the post. When properly
mounted, the hose reel will rest about 4” above the ground.