Innova 2000 Cardiovascular Imaging System
GE Medical Systems
Pre–Installation Manual
REV 5 pim 2337741–100
172
Period Great Poor Yes No
O LPI ++ +=–
Exam room well prepared:
Ceiling: Rails in place & plastic covers available * O O
Ceiling light agreed by radiologist * O O O O O
Wall , Floor: Raceways, conduits in place * O O O O O
Floor: Anchor holes done for gantry (Qty 16) & table (Qty 4) * O O O O
Wall, Floor: Raceways , conduits in place for Accessories &
options (Injector, Extra monitors, ECG, )
* O O O O O
Windows: reduced light with black curtains * O O O
Gases: available on wall, optionally on anesthesia support * O O O O O
User power plugs with ground connected to our reference * O O
Anesthesia support ground or Injector ground connected to our
reference
* O O
Be sure that examination room complies with the 27°C max * O O O O O
Technical area ready:
Wall / floor:
Raceways, conduits in place for cable routing the way
through to ceiling, gantry and control booth
* O O O O O O O
False floor installed for easy access to cables * O O O O O
Cable access ready for the 4 cabinets and the 2 conditioners * O O O O O
Humidity / temperature – is AC completed
Be sure that the temperature in the technical area will not
exceed 32°C (for 7.5kW)
* O O O O O O O
Electrical:
PDB cabinet or equivalent in place * O O
Cabling done for ON/Off room button, Injector power, emer-
gency stop, X–ray on room light
* O O
Direct phone line available * O O
Shelves for documentation and local service tools * O O
Control Booth ready:
Wall floor:
Raceways, conduits in place for cable routing (from technical
area & under table top)
* O O
False wall available behind table top to mask power boxes
and cables
* O O O O O
Table top:
Large enough to support peripherals >1 M
2
(1,5 *0,6m mini) * O O
Holes in table top to mask the cables under the table * O O O O O
Others:
Paints & flooring finalized * O O O O O
Black Circle Qty :
A B C D E F G
A – G =
Pre–Installation could start if: Column F = 29
When System is powered up for the first time, the completed form shall be returned to:
BODELET Philippe GEMS Fax: (33) 01 30 70 95 90 through June 2001
Difficulty of installation = (2 x A) + B – C – (2 x D)
> 24 = Okay
18 – 24 = + 1 day to complete
12 – 18 = + 2 days to complete
6 – 12 = + 3 days to complete
< 6 = + 4 days to complete.