2.2.6 Vivid E9 Ultrasound Layout
On the application defined Vivid E9 positions of the Structural Heart procedures, the 3.5 m
power connection cord limits the location of the power access point. For the minimal
perturbation of the layout, the 3 Vivid E9 connection cables (power, network and the LDM image
link ) shall run close to each other, and shall be directed to a connection area on the head end
wall of the patient room as close to the floor as it is possible, in order to keep the cables on the
room floor.
For information concerning cable conduit from technical room to head end wall of the patient
room, refer to Chapter 5, Cable Channeling.
Illustration 2-63: Vivid E9 Layout (Positioner not shown)
NOTE: The power and the network connection cables belong to the Vivid E9, and they shall
be disconnected from the wall acess sockets before moving the scanner out of the
application positions.
On the other hand, the LDM image link cable shall be disconnected from the back of
the Vivid E9, and rolled up on the cable hooks on the wall.
Innova
TM
IGS 520, Innova
TM
IGS 530, Innova
TM
IGS 540 Pre-Installation Manual
Direction 5499972-1-1EN, Revision 2
Chapter 2 Equipment Requirements 123