3.3.5.3 Specific Prerequisites for Installation Configuration #2
Verify the following items only in the case of Installation Configuration #2 with ECG Device in
Exam Room:
1.
Check the environment of the ECG Device module located in Exam Room provides enough
space to install the physio module at a max distance of 1 meter.
2.
Check enough space can be managed to properly route/hide Physio cable (Physio-to-
Hubican) at table base area.
3. Check the conduit normally designed for MacLab signal cables is present (see conduit
illustration in Chapter 5, Cable Channeling).
3.3.6 Large Display Subsystem option
NOTICE
General safety instructions
Move the LD Cabinet & LD Monitor in an upright position in their original
packages to the final destination room. To lift the LD cabinet, use a forklift or
lifting belts with spreader bars.
Check for sufficient floor and elevator loading capacity.
Check the integrity of the LD Subsystem equipment carefully.
If you notice visible damage, do not install or start the LD Subsystem
equipment. Contact the nearest Service Center immediately.
All installation, maintenance and service work should be performed by
qualified Service personnel.
Innova
TM
IGS 520, Innova
TM
IGS 530, Innova
TM
IGS 540 Pre-Installation Manual
Direction 5499972-1-1EN, Revision 2
Chapter 2 Equipment Requirements 159

Table of Contents

Related product manuals