Ensure sufficient cable length on the Procedures Room end of the cables according to the
table below
Cable Free length from the conduit exit
S5I GE PIM cable * 2.4 m (8’)
FFR cable for Pimette ** 0 m (0’)
Control Station cable 2.1 m (7’)
Joystick cable 2.7 m (9’)
ECG cable Depends on the ECG location
* Consider the 3 m length of the short cable, if the split cable preinstallation exists.
** Pimette has 3 m cable.
NOTE:
The incorrect cable length might cause reliability issues during the operation !
Make sure that the out of conduit parts of the cables with the connectors are properly protected
during the rest of the installation.
2.4.4.2.3 For IVUS Rev 3 option
Refer to Volcano s5i Imaging System Integration in IGS Systems - Service Manual.
2.4.5 Vivid E9 Ultrasound Option
Vivid E9 connection with LDM needs a conduit between the Technical Room (LDM cabinet) and
the Vivid E9 cables access point on the head end wall, close to the room floor and aligned with
the Patient table centerline (see Illustration 5-19).
In case if there is an existing floor conduit for the LDM linkset cables with an exit close to the
Patient Room wall, it is possible to use this duct for the Vivid E9 LDM image link, and continue
with a wall conduit to reach to the Vivid E9 cables access point on the head end wall of the
Patient Room.
For Vivid E9 power connection preparation, please refer to
VIVID E9 Service Manual GA091568
Electrical requirements section.
For Vivid E9 network connection preparation, please refer to
VIVID E9 Service Manual
GA091568
Insite/Network Connection section.
Innova
TM
IGS 520, Innova
TM
IGS 530, Innova
TM
IGS 540 Pre-Installation Manual
Direction 5499972-1-1EN, Revision 2
230 2 System Cable Information