Chapter 7 Appendix
1 PIST0021 - US Fluoro UPS and PDB connection
1.1 Personnel Requirements
Personnel
Requirements
Preliminary Reqs Procedure Finalization
1 Not Applicable 1 hour Not Applicable
1.2 Preliminary Requirements
1.2.1 Tools and Test Equipment
Item Qty Effectivity Part# Manufacturer
Standard Service
Engineer’s toolkit
1 - - -
1.2.2 Required Conditions
Condition Reference Effectivity
The PDB is already installed - -
Power cables are as follows: (1) From
PDB to UPS rectifier input = 4x6 AWG
recommended (4x3 AWG max) (3ph +
PE). (2) Bypass = 5x8 AWG
recommended (5x3 AWG max)(3ph + N
+PE). (3) From UPS output to PDB = 5x8
AWG recommended (5x3 AWG max)(3ph
+ N+PE)..
-
-
Cable sizing shall follow local
requirements.
- -
Power cable Mechanical Terminals
Torque Specification: < 3 Nm / < 27 lb.in
for 20 AWG to 3 AWG.
- -
Check the UPS shipping date marked on
the packaging label. Commissioning of the
UPS must be performed within 3 months
after that date.
-
-
Innova
TM
IGS 520, Innova
TM
IGS 530, Innova
TM
IGS 540 Pre-Installation Manual
Direction 5499972-1-1EN, Revision 2
Chapter 7 Appendix 237

Table of Contents

Related product manuals