GE HEALTHCARE
DIRECTION FC091194, REVISION 11 VIVID 7 SERVICE MANUAL
Chapter 4 - Functional Checks 4 - 5
4-2-2-2 Turn Unit On
1.) Switch ON the Mains Power Circuit Breaker at the rear of the unit.
You should hear a “click” from the relays in the AC Power/AC Controller and the unit is ready to boot.
NOTE: If the unit has been in the OFF condition for an extended period of time, (3 to 5 days or more), the unit
may not boot, or may beep when turned on.
2.) Press once on the ON/STANDBY
key on the Operator Panel to boot the unit.
During a normal boot, you may observe that:
a.) The unit’s ventilation fan starts at full speed, but slows down after a few seconds (listen to the
fan noise).
b.) Power is distributed to the peripherals, Operator Panel (Console), Monitor, Front-End
Processor and Back-End Processor.
c.) Back-End Processor and rest of Scanner starts with the sequence listed in the next steps:
d.) Back-End Processor is turned ON and starts to load the software.
e.) The Start Screen (Vivid) is displayed on the monitor
Figure 4-3 Switch Mains Power Circuit Breaker ON
.
Figure 4-4 Press the On/Standby key on the Operator Panel once to boot the unit
Mains Power Circuit Breaker in ON position