IRECTION FQ091019, REVISION 2 VIVID Q N SERVICE MANUAL
7-50 Section 7-4 - Performing Front End (FE) Diagnostics
As the testing sequence progresses, the progress bar will advance to reflect the test progress.
Status indicators in the Data Flow map corresponding to the various system components will be
highlighted in the appropriate color to indicate the current test status, as follows:
Green: All recommended tests for these components have been completed and no problems
were identified.
Red: Problems were identified in these components during the performance of the test.
Yellow: The tests executed so far on these components have passed, but not all
recommended tests have been performed.
6.) At any stage, trackball to the Pause button and press Set, if required.
7.) To resume testing (from the point where you paused), trackball to the Start button and press Set.
When the System BF Digital Test sequence is complete:
- the Diagnostic Test window displays the Finished message
- the View Test Log window opens automatically, listing all tests performed and showing details
of which tests passed or failed, as shown in the example in Figure 7-25.
8.) If necessary, use the scroll bars and/or arrows to scroll through the list of Test results.
NOTE: For this test, there are two reports (MLA0 and MLA1) which is listed in Reports on the right. By
default, the MLA0 report is displayed in the Reports window below (Figure 7-25).
9.) To view the MLA1 test results, select MLA1 test results under Reports.
The MLA1 test results are displayed in the Report Window, as shown below.
Figure 7-25 View Test Log - System BF Digital Test (MLA0)