EasyManua.ls Logo

Gehl RS6-34 - Fuel Shut-Off Solenoid Test

Gehl RS6-34
292 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
RS5-34 Telescopic Handler ELECTRICAL
PRINTED IN U.S.A. 301-16 913241
Template
Name:
OML
_
2
_
col
907871E
Template Date: 1997_02_12
Alt
=
to
hide
template
information
Alt+ to display template information
FUEL SHUT-OFF SOLENOID TEST
STEP 20
G0805165
Install the positive (+) test lead to the fuel shut-off
solenoid. Turn the key switch to the ON position. The
multimeter should read 12 to 13 volts.
If there is no voltage, proceed to the next step.
If there is 12 to 13 volts, but the engine will not start,
replace the fuel shut-off solenoid valve.
STEP 21
G0805166
Check the fuel shut-off solenoid fuse (1) and test
power to the fuse (Step 4) and ignition relay (2)
(Steps 5 and 6).
If the fuel shut-off fuse and ignition relay are
operating properly, repair or replace the red wire
between the fuse and the fuel shut-off solenoid.
1
2