KB300 / KB350 with FS560
Translation of the original operating instruction and spare parts list
- 26-
5006892-01
BA-E
®
Note: Vacuum is built up faster and safer if the pipe-surface is wetted with water before
attaching a pad.
4.3.4 Fixing with dowels
Set up of the machine on walls or flat surfaces one can choose two ways: Dowel plates or dowel base.
• Dowel plates are attached with bolts to the pipe base.
• Drill dowel holes, mount the dowel and set up the machine with bolts into the dowels. Please follow the
instructions of the dowel-producer!
• Use screws with a minimum length of 140 mm (51/2") when using dowel plates.
• Dowel base is consisting of 2 L-formed plates. The dowel base is attached into the holes of the pipe base,
so first the pipe-base has to be removed and then the two dowel base-plates are mounted instead of the
pipe base.
4.3.5 Fixing with vacuum hold down
• Remove the ground frame and place the machine with the pipe base onto the pipe.
• Attach the vacuum pads to the left and to the right of the pipe-frame, but do not tighten the bolts yet!
• Start the vacuum pump and wait until gauge on vacuum pump shows a minimum of 0,7 bar (10 PSi).
• Connect one male coupler of the vacuum system to one of the vacuum pads and wait until vacuum is built-
up.
• Repeat this operation to the second vacuum pad. Tighten all the bolts that connect the pads to pipe frame.
Fixing with dowel plates
Fixing with dowel base
Note: Read and observe the operating instructions to the vacuum suction plates!