Unit Installation
(2) In order for better sealing effect, before connection they should be wrapped with Teon tape.
(3) After the connector, the water valve and the water pipes have been nished, you may start the
water pump and see if they leak or not.
(4) Insulate the water valve and the pipe with sponge.
L
N
N(1)
2
L
N
(N)
(L)
PE
P
E
XT1
Main unit
Power line
Outlet pipe
Inlet pipe
PVC sleeve
Power
Water
valve
(5) When the water pipe and water valve have been installed, connect the connection line of the valve
to the wiring board of the unit.
(6) Check the wiring carefully and then start the water pump and unit to see if they work normally.
Notices:
(1) The water valve should be installed as the following statement; otherwise it would affect the normal
operation.
It is not allowed to directly insulate the connection
line of the actuator and the water pipe together,
otherwise it would lead to shortcutting of the water
valve which would affect its service life.
Connection line of the actuator
Insulation
sleeve
Water pipe
Put the connection line through the PVC
pipe and then bind them with the insulation
sleeve.
Connection line
of the actuator
PVC pipe
Insulation
sleeve
Water pipe
Never install the valve downwards, otherwise the
condensate would ow into the valve and damage
the valve or then would lead to shortcutting or re
hazards.
The main body of the valve should be
installed upwards and the power lines should
be arranged above the water pipe.
Insulation sponge
Do not cover fully the valve with the
insulation sponge; otherwise it would
lead to poor heat radiation and even
re hazards.