3. Installation
The system may comprise of the following units:
Blast Cabinet/Cyclone/Dust Collector
Flexible extraction hoses, sealing bands and hose clamps are supplied to connect these together.
Remove packing materials and check inside blast cabinet for loose items.
3.1 Location
The equipment must be located on a clean, dry surface.
Locate the cabinet in the required position and orientation; always allow sufficient room around the
units to fully open doors and to give access for operation and maintenance.
Care should be taken to ensure all parts of the system are level
3.2 Assembly
Hoses with media flowing through them should only have smooth flowing curves in them.
If your system only comprises of a blast cabinet and dust collector then:
Connect the flexible extraction hose from the cabinet outlet to the dust collector
inlet using the sealing bands and hose clamps supplied.