ES0755  rev A      1/11
4
mating surfaces.
2.  Prepare the column base for mating
•  Stone and clean thoroughly the mating ange surface. This is an extremely important step 
that must be well and properly done before the bases are moved into position with respect 
to each other. (Failure to properly prepare the surfaces and preserve their cleanliness 
may require separation of the main components for corrective action).
•  Check the thread of each hole in the column base, ensure there is no damage.
•  Ensure the air/electrical/oil lines and connectors are safely away from the mating surfaces.
3.  Place the column base assembly in position. Rough level by measuring from the oor to the bot-
tom of the base (very close to 2 inches). Each of the leveling screws and pads should be in place 
at this time and it is advisable to take the measurement at each leveling screw location for best 
results. This will ensure that the nal leveling procedure will go more quickly and that the coolant 
tank will properly t beneath the coolant discharge. Loosely screw the jam nuts onto the leveling 
screws.
4.  Place the table base assembly in position. When placing the table base in position with respect 
to the column base, it is important that the two mating anges be as parallel as possible (verti-
cally and horizontally). Be certain that each of the nineteen screws are actually engaged in the 
threads, and that when the column base is in place and the mating surfaces are in contact that 
each screw is free to rotate. Rough level by measuring from the oor to the bottom of the base 
(very close to 2 inches). Each of the leveling screws and pads should be in place at this time 
and it is advisable to take the measurement at each leveling screw location for best results. This 
will ensure that the nal leveling procedure will go more quickly. After rough leveling, fully tighten 
the connecting screws to be sure the mating surfaces are in full contact, and then loosen them 
all approximately 3 full turns. Be certain that the connecting screws are still free to rotate (do not 
leave the connecting bolts tight at this time because the machine still must be nal leveled and 
squared).
3.1 initial setuP
WARNING! 
At this point, there should be NO electrical connection to the machine. The electrical panel should 
be closed and the three latches on the door should be secured at all times except during installation 
and service. At those times, only qualied electricians should have access to the panel. When the 
main switch is on, there is high voltage throughout the electrical panel (including the circuit boards 
and logic circuits) and some components operate at high temperatures. Therefore, you must exer-
cise extreme caution when you are working in the panel.
1.  Set the main switch at the upper right of the electrical panel on the back of the machine to OFF.
2.  Unlock the cabinet with the key and open the door.