3. Duct type unit of high static pressure AD322FIAHA, AD362FIAHA, AD452FIAHA
check opening
above 100
above 900
air outlet
air inlet
(600x600)
above 300
above 200
ceiling
Requited installing space (unit: mm)
Preparation before installation
(1) Ubiety before hosting screw stem (unit: mm)
below
above
1103
794
360
250
1270
853
(2) If necessary, make hole on the ceiling for installation. (If the ceiling is available).
For the dimension of opening on the ceiling, please refer to the right diagram. Before installation, prepare all the pipelines (refrigerant, water drain) and wires (connecting wire of remote controller, connecting wire of indoor unit group and outdoor unit group) to be connected with indoor unit group so as to
immediately connect with indoor unit after installation.
When make hole on the ceiling, it may be necessary to reinforce the ceiling to maintain the leveling of the ceiling
and prevent the ceiling from vibration. For more detail, consult the constructor.
(3) Installing the hoisting screw stem
(Use M10 bolt)
In order to bear the weight of the unit group, the anchor bolts should be used when there is the ceiling. For new
ceiling, the sunk bolts, embedded bolts or other parts provided on the spot should be used. Before continuing to
install, adjust the clearance between the ceiling.
access hole anchoring
access hole plug
plug
concrete
hosting screw
stem M10