91
4000392150 E02.16 USA / GB
Control-Filling-up-Battery charge
Battery
E018
10 min
Control-Filling- up-Battery charg e
Battery
1 - You will need
2 - Preliminary procedure
1. Place the machine in maintenance configuration. 3.3.1-Placing the machine in maintenance
configuration
3 - Control
Loosen the caps located on the top of the battery.
The level of electrolyte in the battery must be approx. 0,01 m(0 ft39 in) above the plates.
4 - Filling-up
• Standard tool kit
• Protective goggles
• Gloves
• Place barriers around the perimeter of the
work area
The battery manufacturer's safety instructions must be followed.
Loosen the caps located on the top of the battery.
If the level of electrolyte is below the level of the plates :
1. Top up with distilled water.
2. Refit and tighten the battery caps.