Total Station Manual
- 137 -
In doing stakeout, center pile should be done first, then left and right pile.
Like point stakeout, there are three methods to do stakeout:
Method
Definition
Display
Polar
staketou
Hz
Direction difference:
Positve if measuring point
being right side of target
point.
Horizontal distance
difference: Positive if
measuring point far away
target point.
Height difference: Positive
if measuring point above
of target point.
ALL DIST REC EDM
[Road Stakeout] 1/3
Pt.
T.H.
Hz
---
---
K+12.0
2.000 m
13°3910
------
------