Total Station Manual
- 84 -
In the process of staking out,
if using the Repeat
Measurement or Tracking
Measurement, the calculation
of the differences between
measured point and stakeout
point can be displayedin real
time and convenient.
○
6 It means the current prism
position is effective stakeout
point while both the△Y/E and
△X/N are 0.
△Z/H: Display as dig or fill
data.
△Z/H is positive: The value
expresses the depth of
needed to dig.
△Z/H is negative: The value
expresses the height of
needed to fill.
*
ALL DIST REC
[Stakeout] 3/3
Search :
Pt. :
T.H :
Y/E :
X/N :
Z/H :
5
2.000 m
0.000 m
0.000 m
-1.209 m
○
8 Now itfinishes staking out
a point.Repeat the previous
steps to stake out next point.
*
ALL DIST REC
[Stakeout] 3/3
Search :
Pt. :
T.H :
Y/E :
X/N :
Z/H :
6
2.000 m
------
------
------