10
INSTALLATION & MAINTENANCE MANUAL
5. Installation Work
5.1 Zone Interface Box Installation
5.1.1 Place to Install
Select a place that meets following requirements:
(1) Refer to the clause "1. Safety Summary" of this installation manual.
(2) Place where Zone Interface Box can be securely fixed.
(3) Place where the Zone Interface Box cannot be tampered with.
5.1.2 Installation Procedure
(1) Minimum installation space requirements as illustrated in figure 5.1.
≥600
≥50
≥50
≥50
≥100
Unit: mm
Figure 5.1 Installation Space
(2) Installation on a flat surface
a. The Zone Interface Box can be mounted in the horizontal or vertical position. When installed in
the vertical position, please make sure that the wire outlets are facing downwards.
CORRECT INCORRECT INCORRECT
Wire outlets face the floor.
Figure 5.2 Direction for Installing Zone Interface Box
b. Firmly fix Zone Interface Box on a flat surface through six holes with M5 screws (M5 screws are
field-supplied).