Floor
LoadRating
(kg/m2)
Required Clearance (a+b) m
c= -0.3 c=0 c=0.2 c=0.4 c=0.6 c=0.8 c=1.0 c=1.4
600 0 0 0 0 0 0 0 0
500 1.0 0.4 0.1 0 0 0 0 0
450 1.7 1.1 0.7 0.4 0.2 0 0 0
400 2.6 1.9 1.5 1.2 0.9 0.6 0.3 0
350 4.0 3.1 2.6 2.2 1.8 1.5 1.2 0.7
300 6.2 5.1 4.4 3.9 3.4 3.0 2.6 2.0
Notes;
1. Actual clear
ances for installation should be determined after consulting with the
construction specialist r
esponsible for installations in the building. Clear
ances can
vary depending on the size/layout of the system and building conditions.
2. When various congurations of stor
age systems are arranged in a row, clearance
values based on the largest storage system conguration should be used.
3. For easier maintenance operations, make clearance (c) as large as possible.
Seven-rack configuration
The following gure shows the service clearances for a seven-rack conguration.
Seven-rack conguration
Chapter 4: Site preparation specications
Hitachi Virtual Storage Platform G1000, G1500, and VSP F1500 Hardware Guide 101