2 Unit Installation
26
SMGB0064 rev.0 - 08/2011
3 Example of xing outdoor unit by anchor bolts.
1. Max. 17 mm (After cut “A”)
2. Concrete
3. Anchor bolt
B: Cut this portion when this type of anchor bolt is used. If not
done it will be difcult to remove the service cover
B
1
2
3
4 Provide an adequate drainage around the foundation. When installing the unit on a roof or a veranda drain water may
turn to ice in a cold morning. Therefore avoid draining in an area where people often use because it is slippery. In case
of installing such a place provide the additional drainage around the foundation.
1. Drain hole (30x80)
2. Drain hole (3-30x80)
3. Front side
2
3
5 The whole of the base of the outdoor unit should be installed on a foundation. When using vibration-proof mat it should
also be positioned the same way. When installing the outdoor unit on a eld-supplied frame use metal plates to adjust
the frame width for stable installation as shown in Figure.
1. Outdoor unit is unstable
2. Frame
3. Outdoor unit is stable
4. Metal plate
A. 57 mm. Base width of outdoor unit
B. 40 mm Frame width (Field-supplied)
C. 100 mm or more Metal plate
A
B
2
1
A
C
2
3
4
INCORRECT CORRECT
• Recommended Metal Plate Size:
- (Field-Supplied) Material: Hot-Rolled Mild Steel.
- Plate (SPHC) Plate Thickness: 4.5 T
120
60
(560)
70
420
70
20
14
R
4-C10