R301.1 Experion C300 Controller User's Guide 141
11/06 Honeywell
Load C300 Controller Configuration
This section includes information about tasks associated with loading C300 Controller
configuration using Control Builder. The following topics are presented here. Click on
the topic to view it.
Topic
About load operations
Initial load order guidelines
Load components from Project
Load With Contents command
Reloading components from project
Restrictions and conditions for reloading operations
Upload to the Monitoring database
About load operations
The Experion system provides the ability to build control strategies offline, without being
connected to the actual field components. The process of transferring the control strategy
to the "live" working components in the field is called the load operation.
The load operation functionally copies configuration data from the control strategy that is
stored in the Engineering Repository Database (ERDB) to the assigned field component
in the system architecture. It indirectly assures that the planned system matches the actual
one. The communication addresses and physical location assignments specified for
components through Control Builder configuration must match the actual addresses and
locations of components in the system.
Loaded versus project database versions
The master control strategy, stored in the Engineering Repository Database (ERDB), is
configured and edited through the Project tree. Once the contents of the control strategy
are loaded from Project to the applicable components, a loaded version of the Project or
master database is created. The loaded version of the database is viewable only through
the Monitoring tree and supports only minimal editing of the control strategy
configuration data.
The following commands are included in the Control Builder Controller menu to
synchronize data in the loaded database with the data in the Project/master database.