C300 Controller installation
C300 Controller assembly
R301.1 Experion C300 Controller User's Guide 23
11/06 Honeywell
Table 3 C300 Controller IOTA Board Connector Summary
C300 IOTA Board Description
F1 Fuse
IOL1A, IOL1B (BLUE)
IOL2A, IOL2B (GRAY)
Redundant IOLINK connectors for IOLINK 1 and
IOLINK 2
FTEA, FTEB
Fault Tolerant Ethernet (FTE) network
connectors
FTE A network cables are Yellow.
FTE B network cables are Green.
REDUNDANCY Redundant private path cable connector.
Redundancy cable is Orange
MEMORY HOLD-UP Battery Backup cable connector
Battery cable is a twisted pair.
GPS (Currently not used) GPS cable connector
FTE DEVICE INDEX
100, 10, 1
Three rotary decimal switches used to set the
FTE network address (Device Index) of the
controller.
See Step 9 of the C300 Controller Installation
procedure for setting the address.
Prerequisites
Before you install the C300 Controller you should have:
• A control cabinet installed with appropriate carrier hardware for mounting Series C
control hardware.
• A Series C power supply and optional battery backup hardware installed in the
cabinet.
• Installed pair of Control Firewall (CF9) assemblies.
• The necessary parts for installing C300 Controller to the control system. See Series
C System Cabling in the Control Hardware Planning Guide for cable hardware