Conversion Factors
Refrigeration
1 watt = 0.86 kcal/hour
1 watt = 3.412 Btu/hour
1 watt = 2.843 × 10-4 tons
1 ton = 200 Btu/minute
1 ton = 12,000 Btu/hour
1 ton = 3,517.2 watts
Metric Equivalents
1 centimeter = 0.3937 inch
1 meter = 3.28 foot
1 meter = 1.09 yards
1 in. = 2.54 centimeters
1 ft. = 0.305 meters
1 CFM = 1.7m
3
/hour
kVA conversions
Three phase
kVA = V × A × √3 / 1000
Single phase
kVA = V × A / 1000
Formulas
kVA = voltage × current (amps)
Watts = VA × PF
Btu = Watts × 3.41
ºC = (32 + 1.8a) ºF
Example of an Installation Schedule
The following schedule lists the sequence of events for a typical system installation:
Sixty days before installation
Floor plan design is completed and mailed to HP (if required to be an HP task).
Thirty days before installation
Primary power and air-conditioning installation are completed.
Telephone and data cables are installed.
Fire protection equipment is installed.
Major facility changes are completed.
Special delivery requirements are defined.
Site inspection checklist is completed. See Table 1-7 and Table 1-8 (page 33) for sample
customer information forms and site inspection checklists.
Delivery survey is completed. See Figure 1-13 (page 36) and Figure 1-14 (page 37) for
a sample delivery survey.