Appendix G
Connecting Multiple SPU Cabinets
Preparing Cabinet 1 for Connection
185
Preparing Cabinet 1 for Connection
Before you connect the cabinets, prepare Cabinet 1, the right cabinet (as you face the front of the both
cabinets):
Step 1. Ensure that the UGUY is set as Cabinet 1.
The cabinet number is clearly marked on the UGUY board, just below the Cabinet Number Switch.
Figure G-4Cabinet Number Location
If the switch is not set to 1, change it by turning the thumbscrew.
Remove the latch catch and associated hardware first; they will be needed later.
Step 2. Using a T20 driver, remove the cable access panel on the right as you face the rear of Cabinet 1.
Keep the flathead screws.
60IN019A
10/6/00
Cabinet 1 (Right)
Rear View
Cabinet Number Switch
UGUY
UGUY
See Detail
L3-L1
L2-L3
L1-L2
L1-L2
L3-L1
L2-L3