Standard Operation Procedure
Document No. Cyclone 15B FA DIS ASS’Y SOP Station :
Name : Ver. : Date :
Step:
Notes : If finding anything uncommon, notice foreman or assistant at once.
Holding fixture list (holding fixture standard)
Qty
Holding fixture list (holding fixture standard)
Qty
Tabulator:
Issue department:
Alicia Chien
NPSU-PPE
Auditor :
Stanley Chen
disassembly BTCB
1. Separate BTCB from TPCB. (Fig.1)
Fig.1
Fig.2
17(1/1)
0.1
2013/08/23
Start from here