• The front drive bays are fully populated with 12 LFF or 24 SFF drives.
• High performance fans are installed in all fan bays.
Procedure
1. Power down the server.
2. Remove all power:
a. Disconnect each power cord from the power source.
b. Disconnect each power cord from the server.
3. Do one of the following:
•
Extend the server from the rack.
• Remove the server from the rack.
4. Remove the access panel.
5.
Do one of the following:
For primary bays, remove the riser cage.
For secondary bays, remove the rear wall blank.
Hardware options installation
85