Hardware options installation 111
o
For rack models, install the security bezel ("Security bezel option" on page 50).
GPU power cable option
For more information about product features, specifications, options, configurations, and compatibility,
see the product QuickSpecs on the Hewlett Packard Enterprise website (http://www.hpe.com/info/qs).
To install a third 150W GPU, a third power supply must be installed.If more than two power supplies are
needed, then the x4 Redundant power supply option ("x4 Redundant Power Supply backplane option" on
page 125) must be installed.
The server supports up to four graphic cards, install graphic card options in PCIe slots 1, 3, 6, or 8.
IMPORTANT: If installing a graphic card for the first time, we highly recommend that you
contact HPE Technology Services for assistance.
To install the component:
1. Back up all server data.
2. Do one of the following:
o For tower models, open and remove the tower bezel ("Remove the tower bezel" on page 31).
o For rack models, if installed, remove the security bezel ("Remove the security bezel (optional)"
on page 31).
3. Power down the server (on page 30).
4. Remove all power:
a. Disconnect each power cord from the power source.
b. Disconnect each power cord from the server.
5. Do one of the following:
o For tower models, place the server on a flat, level surface with the access panel facing up.
o For rack models, extend the server from the rack (on page 34).
6. Remove the access panel (on page 32).
7. Remove the air baffle (on page 34).
8. Remove the fan cage (on page 37).
9. Disconnect all cables connected to the system board.
10. Remove the system board:
a. Loosen the two system board thumbscrews.