4.6.1 Commissioning the Emergency Light (CE)
Prerequisites
The sockets of the emergency light have been powered on.
Preparations
Tools: step ladder, Phillips screwdriver
Documents: drawings and parameters for power supply and distribution as well as
re extinguishing
Skill requirement: re engineer
Procedure
Step 1 Turn
o the upstream switch for the emergency light power cable.
Figure 4-5 Emergency light
Step 2 Remove the protective cover of the emergency light.
Step 3 Remove the red pin of the emergency light. The emergency light turns on.
Figure 4-6 Removing the red pin
Step 4 Reinstall the protective cover of the emergency light.
FusionDC1000A Prefabricated All-in-One Data
Center
Commissioning Guide (IT Scenario) 4 Commissioning Core Devices
Issue 02 (2022-12-15) Copyright © Huawei Digital Power Technologies Co., Ltd. 48