Figure 4-1 Mounting structure
4.2.3 Clearance Requirements
Reserve sucient clearance around the Smart PCS for installation and heat
dissipation.
Figure 4-2 Installation clearance (support-mounting and wall-mounting
scenarios)
For ease of installation, cable connection, and maintenance, reserve 600–730 mm clearance
underneath. For further questions regarding the clearance, consult local technical support
engineers.
When installing multiple devices, install them in horizontal mode if sucient
space is available and install them in triangle mode if no sucient space is
available. Stacked installation is not recommended.
LUNA2000-200KTL-H1 Smart Power Control System
User Manual 4 Installation
Issue 08 (2024-01-23) Copyright © Huawei Technologies Co., Ltd. 30