After the cleaning is complete, reinstall the bae plate to the air intake vent.
Tighten the screws with a torque of 1.2 N·m.
Removing the Protective Cover from the Air Exhaust Vent
Figure 8-2 Removing the protective cover
After the cleaning is complete, reinstall the protective cover to the air exhaust
vent. Tighten the screws with a torque of 1.2 N·m.
8.2 Powering O the System
Precautions
To prevent personal injury and equipment damage, perform the following
procedure to power o the Smart PCS for troubleshooting or replacement.
● If the DC switch between the Smart PCS and the DC LV Panel busbar has been
turned o automatically, do not turn on the switch before the fault is rectied.
● If the AC switch between the Smart PCS and the power grid has been turned
o automatically, do not turn it on before the fault is rectied.
● Before power-o for maintenance, do not touch the energized components of
the Smart PCS. Otherwise, electric shocks or arcs may occur.
Procedure
Step 1 Wear proper PPE.
LUNA2000-200KTL-H1 Smart Power Control System
User Manual 8 Device Maintenance
Issue 08 (2024-01-23) Copyright © Huawei Technologies Co., Ltd. 71