Step Task Power-On Operation
7 Powering on the
SUN2000
Select a power-on method based on the
inverter model.
Method 1:
1. Set the DC SWITCH to ON. When you hear
a click, the switch is completely turned on.
2. The indicator is not steady red.
Method 2:
1. Set the DC SWITCH 1 (MAIN SWITCH) to
ON. When you hear a click, the switch is
completely turned on.
2. Check the status of the PV connection
indicator. If it is steady green, set DC
SWITCH 2 and DC SWITCH 3 to ON.
3. Check that other indicators are not steady
red.
Note: For details about the switch layout and operations of the devices prepared
by the customer, see the documents provided by the vendors.
4.2 Deployment Commissioning
4.2.1 Preparations and WebUI Login
The SmartLogger WebUI is used for power-on and commissioning. For details
about the preparations and WebUI login, see the SmartLogger3000 User Manual.
4.2.2 Preparations Before Deployment
Step 1 Click Maintenance, choose Device Mgmt. > Connect Device, and check that the
devices are connected.
Figure 4-3 Checking device connection
1. To manually add an IMD, click Add Devices and set IMD access parameters.
Commercial and Industrial Microgrid Energy Storage
Solution
Quick Guide (With Third-Party Microgrid Central
Controller) 4 System Power-On and Commissioning
Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd. 25