Figure 4-4 Upgrading software
Step 4 Clear alarms.
Clear the alarms that aect topology identication by referring to C List of
Alarms Aecting Topology Identication, and then search for the devices.
----End
4.2.3 Commissioning Using the Deployment Wizard
Step 1 Set basic parameters.
Figure 4-5 Setting basic parameters
Step 2 After the ESS is started, you are advised to wait for a period of time greater than
or equal to Device disconnection time (choose Maintenance > Device Mgmt. >
Connect Device to view Device disconnection time), and then click Search for
Device to check cable connections and allocate addresses.
Commercial and Industrial Microgrid Energy Storage
Solution
Quick Guide (With Third-Party Microgrid Central
Controller) 4 System Power-On and Commissioning
Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd. 28