Figure 4-6 Searching for devices
NO TE
During the process of Search for Device, do not perform upgrade operations (such as
upgrading through the app, management system, or WebUI).
When you click Search for Device, cable connections (DC and AC) will be checked
before device search (not applicable to third-party devices), and device addresses will be
automatically allocated.
After the cable connection check and device search are complete, if a cable connection
alarm is generated, you can click the alarm icon to view the corresponding alarm
information.
If an alarm is generated when the cable connection check fails, click the alarm icon
to view the alarm cause and handling suggestions. After the fault is rectied, click
Search for Device again to check the cable connections. For details about alarms, see C
List of Alarms Aecting Topology Identication.
After the cable connection check and device search are complete, click to view the
corresponding topology information.
After a device is added or deleted, you need to click Search for Device again in
Deployment Wizard. Otherwise, the system topology will not be updated.
Step 3 After the device search is complete, set the grid connection state based on site
requirements.
Commercial and Industrial Microgrid Energy Storage
Solution
Quick Guide (With Third-Party Microgrid Central
Controller) 4 System Power-On and Commissioning
Issue 04 (2023-12-18) Copyright © Huawei Digital Power Technologies Co., Ltd. 29

Other manuals for Huawei LUNA2000-200KWH-2H1

Related product manuals